Raffles Marina Lighthouse
 
 
Infrastructure Works Project


In order to keep you fully informed we plan to maintain a pictorial log of works completed and those in progress. This log will be continually updated and is available for you to view at any time via our Website or a link on our fortnightly newsletter.

The project will be split into four mini stages, Works in our Boat House, on the southern end of our promenade, including the removal of the existing fuel tanks, work to the northern section of our promenade and works related to the relocation of our fuel storage tanks.

Infrastructure Works Project Update - 2014
Infrastructure Works Project Update - 2013

18 August 2014

I-beams in place and completed

New fuel tanks installed and road re-leveled

Re-leveled walkway

 

4 July 2014

Replacement of I-Beams

Excavation works to remove old fuel tanks. 

17 June 2014

Lawn re-leveling completed

Outside Marina Bistro Awaiting Top Finishing 

22 May 2014

Lawn re-leveling nearing completion

New Fuel Tank nearing completion

24 April 2014

IWP Upgrading Works 24 Apr 2014

Lawn re-leveling nearing completion

Fuel Tank Relocation nearing completion

7 March 2014

Drainage Works Progress

Awaiting New Top Finish

Fuel Tank relocation

5 February 2014

Realigning drainage

Excavation work continues near Berth B & C.

Near completion of re-alignment works (from Berth D to H).

10 January 2014 – Excavation works continue.

Removal of stone slabs to reconstruct and level the payment (before the lagoon, from Berth C to G).
 
Excavation and levelling of drainage Construction of underground fuel tank base.  

....................................................................................................................................................................................................................................

13 December 2013 – Excavation works continue.

Front of boathouse


Back of the boathouse

Before the lagoon, brick pavement from Berth C to G

....................................................................................................................................................................................................................................

1 November 2013 – Excavation works commenced at the back of the boathouse, and the brick pavement leading to Berth H.

Removal of pavement stones.

Exploring works in the Boathouse.

....................................................................................................................................................................................................................................

4 October 2013 - Preliminary works at the back of boathouse for the new location for the underground fuel tank.

Location for the construction of a trench for the new fuel tank.

Containers are relocated just a short distance away to provide space for site hoarding works.

The area marked in yellow, will be excavated to house the new fuel tank.